For UK construction firms · Sample data

Job programme demo: the job you priced, on a programme

Accepted quotes become a programme without retyping anything: activities, dates, stage payments and the cash position, all from the priced lines.

Step 1 of 3

The job you priced

The quote's own lines become the programme, so nothing is typed twice.

Example Flooring Ltd · Jobs

Surgery refurb for Example Builders Ltd

Quote EF-Q-2026-3502. On site Thu 10 Dec to Thu 31 Dec 2026, 14 working days, £11,950.39 ex VAT.

This is the first enquiry in the estimator's inbox, priced at the library rates. Price a job in the quoting demo and it's scheduled here instead.

  • ✓ Each activity's cost and charge are the quote's own lines, so the programme adds up to the quote.
  • ✓ Lengths come from how much a crew lays in a day, with drying time after the smoothing compound.
  • ✓ Starts two weeks out, skipping weekends and bank holidays. Stage payments fall due as the work completes.

Step 2 of 3

The programme

Drag a bar to move a task or change its length. The dates, critical path and money follow.

Critical path Has float Stage payment Bank holiday

Tasks, dates and money

Task Start Finish Working days Cost Charge Margin
Uplift and dispose of the existing floor (critical) Thu 10 Dec Mon 14 Dec 3 £1,363.80 £1,730.19 21.18%
Moisture test the slab (critical) Tue 15 Dec Tue 15 Dec 1 £180.00 £252.00 28.57%
Smoothing compound and primer (critical) Wed 16 Dec Thu 17 Dec 2 £855.60 £1,069.50 20.00%
Lay safety vinyl (critical) Mon 21 Dec Tue 22 Dec 2 £1,958.40 £2,581.76 24.14%
Lay LVT (critical) Wed 23 Dec Tue 29 Dec 3 £3,940.60 £5,181.34 23.95%
Weld and cove the skirting 2 days of float Wed 23 Dec Thu 24 Dec 2 £570.40 £770.04 25.93%
Trims and thresholds (critical) Wed 30 Dec Wed 30 Dec 1 £281.20 £365.56 23.08%
Snag, clean and hand over (critical) Thu 31 Dec Thu 31 Dec 1 £0.00 £0.00 0.00%
Whole job Thu 10 Dec Thu 31 Dec 14 £9,150.00 £11,950.39 23.43%

Sample job for a fictional flooring contractor. Figures exclude VAT. Yours would show your own jobs, rates and payment terms. Bank holidays from GOV.UK.

Step 3 of 3

Money and cash flow

What the job earns, when each stage payment falls due, and the weeks it runs on your own cash.

Job summary

Duration
14 working days
On site
10 Dec – 31 Dec 2026
Bank holidays inside it
Christmas Day (25 Dec), Boxing Day (substitute day) (28 Dec)
Total cost
£9,150.00
Total charge
£11,950.39
Profit
£2,800.39
Margin
23.43%

Stage-payment schedule

Stage Due on completion Value Cost spent by then Cash position
Stage 1: strip-out and prep complete 30% of the contract sum Thu 17 Dec £3,585.12 £2,399.40 £1,185.72
Stage 2: floors laid 40% of the contract sum Tue 29 Dec £4,780.16 £8,868.80 −£503.52
Stage 3: handover 30% of the contract sum Thu 31 Dec £3,585.11 £9,150.00 £2,800.39

Cash position is stage payments earned minus cost spent, with each task's cost spread evenly over its working days. It ignores payment terms, which push the money later still.

About this programme demo

A quote you win is the start of the work, not the end of it. Here the priced lines become a programme of works: strip-out and prep first, the floors in order, the welder following the vinyl, then snagging and handover. Drag a task and the dates, margin and cash position move with it, because they're calculated rather than drawn. In a tool built for your firm, this comes out of your own quotes, crews and payment terms. See the construction Gantt chart guide for how programmes, critical paths and stage payments work.